Agenda Item #23


Title
ACCEPTANCE OF SUBSTANTIAL COMPLETION FOR RIVERVIEW HIGH SCHOOL - PORTABLE RELOCATION PROJECT

Description
The architect has prepared the Certificate of Substantial Completion and the final punch list.  The project is substantially complete in accordance with the contract documents.  A copy of the final punch list is available for review at the Construction Services Department.

Recommendation
That the work performed by Jon F. Swift, Inc. for the Riverview High School - Portable Relocation project be accepted as substantially complete as of 6/30/2006.

Contact

LEMPE & COLLINS



Financial Impact

Capital:  N/A




Attachment:  BAIenc8-1-2006RHS-PortRelocSC.pdf